We recently delivered LECA® LWA to England's largest parish church Hull Minster with our unique pneumatic delivery facility. Overcoming difficult access to this Grade 1 listed building and delivering at a rapid speed, which was crucial for this groundwork repair. This delivery option significantly reduced man power and also ensured that safe social distancing measures could be maintained.

For this project, LECA® LWA 10-20 aggregate was pneumatically blown in as backfilling material following archaeological excavation works at Hull Minster. LECA® LWA was specified for the groundwork repair because of its lightweight properties and its ability to tackle the possibility of mechanical compaction of the top layer and to reduce the settlement to external areas where paving was proposed to be laid.

For this project, the designers required around 140m3 which included a compaction reduction of 10%. The intention of the project was to carry out backfilling of archaeological excavations up to the formation level and for it to remain whilst further works are carried out over a few months.

FACTS


Amount of material: 140m3 of LECA® LWA (10-20mm)

Interesting Fact:  Overcoming difficult access to this Grade 1 listed building and delivering at a rapid speed, which was crucial for this groundwork repair.

Delivery Method: Pneumatic Delivery

Overview of Project

LECA® LWA was deemed as a suitable solution furthermore due to the pre-compaction of LECA LWA, which expected to be 5%. Moreover, as LECA® LWA requires little compactive force, any sufficient load placed on the compacted material will force the particles into place.

HULL MINSTER GROUNDWORKS PROJECT
HULL MINSTER GROUNDWORKS PROJECT
HULL MINSTER GROUNDWORKS PROJECT
HULL MINSTER GROUNDWORKS PROJECT

Furthermore, as good compaction was required for the final build, on a depth between 300mm and 600mm – using LECA® LWA only required 3 passes of the Light Vibrating wacker plate, which effectively ensured that the material sat in its final resting place. (We often state that compaction is not necessary if the depth is below 300mm, as any capping above will normally force the material in to place.)

About us

#1 supplier of Expanded Clay Lightweight Aggregate in Europe for your infrastructure, housing and water management projects.

More info
alternative text image

Related Downloads

Please register your details first

Areas of interest